| John Fraser Hall
Modernization History |
|
| DATE | DESCRIPTION OF WORK |
| July 1993 | Door & Frame Replacement |
| September 1993 | Scattered Concrete Replacement |
| November 1993 | Air Filtration Unit Installation |
| 1994 | Accessibility Improvements / Elevator Improvements |
| January 1994 | Hoist Installation |
| February 1994 | Elevator Upgrade & Accessibility Improvements |
| January 1996 | Dwelling Unit Cleaning & Painting |
| 1997 | Video Surveillance System Installation |
| 1997 | Window Replacement, A/C Installation, Mechanical Improvements |
| April 1997 | Miscellaneous Building Improvements |
| November 1999 | Dwelling Unit Cleaning & Painting |
| January 2000 | Door Operator Installation |
| December 2000 | Interior Painting & Carpet Installation |
| December 2000 | Installation of Vertical Blinds |
| July 2001 | Dwelling Unit Painting |
| July 2001 | Dwelling Unit Flooring Service |
| July 2001 | Selective Concrete Replacement |
| January 2003 |
Duct Cleaning & Sanitizing |
| 2008-2009 | Comprehensive Modernization |