Hawkins
Village Modernization History
|
|
|
DATE |
DESCRIPTION
OF WORK |
1992 |
Asbestos Removal |
November 1992 |
Comprehensive Modernization |
February 1994 |
Tree Removal |
September 1994 |
Learning Care Improvements |
October 1994 |
Padlock Supply & Delivery |
October 1994 |
Learning Center Improvements |
April 1995 |
Dwelling Unit Cleaning &
Painting |
May 1995 |
Playground Site Improvement |
July 1995 |
Playing Field Improvements |
July 1995 |
Insulated Panel Supply &
Installation |
July 1995 |
Window Screen Supply &
Installation |
July 1996 |
Selective Demolition |
May 1996 |
Tree Service |
May 1996 |
Fence & Sign Installation |
August 1996 |
Fence & Sign Installation |
November 1996 |
Security Screen Installation
at Community Building |
February 1997 |
Site Entrance Wall Construction |
March 1997 |
Handrail Installation |
March 1997 |
Playground Renovations |
May 1997 |
Selective Concrete Replacement |
October 1997 |
Entrance Wall Construction |
1999 |
Installation of Storage
Cabinets in Units |
1999 |
Asphalt Resurfacing |
1999 |
Fence at Ball field |
April 2001 |
4-Kids Learning Center Construction |
April 2001 |
Accessibility Conversions
& Minor Renovations |
July 2001 |
Dwelling Unit Painting |
July 2001 |
Dwelling Unit Flooring Service |
July 2001 |
Selective Concrete Replacement |
July 2001 |
Selective Asphalt Repair
& Resurfacing |
April 2001 |
Accessibility Conversion
& Minor Renovations |
July 2003 |
Selective Concrete Replacement
& Rear Patio Reconfiguration |
August
2008 |
Playground
Safety Surface Repairs |
November
2009 |
Concrete
Stair Demolition |
January
2010 |
Security
Fence Installation |